Instream Works

Fort Macleod Riverbank Stabilization

Ironclad acted as Prime Contractor on the Fort Macleod 2013 Flood Mitigation project for the Town of Fort Macleod, providing general contracting and waterworks construction services. The project involved supplying over 20,000 tons of heavy rock riprap for 1,500 meters of riverbank armoring and significant instream work on the Oldman River.

KEY DETAILS

Contract Value

$3,800,905

Project Owner

Town of Fort Macleod

Completion Date

October 2014

Project Role

Prime Contractor

Scope of Work

  • Supply and delivery of over 20,000 tons of heavy rock riprap
  • 1,500 linear meters of riverbank armoring
  • Restoration on the Oldman River
  • Full-time turbidity monitoring and control
  • Divert and realign the main channel of the Oldman River in two locations within strict RAP periods.

Resources & Challenges

  • Total Crew: 13 Persons
  • Equipment Used:
    4 Excavator, 4 Rock Trucks, 2 Loaders, 1 Skidsteer, 35 Highway Trucks
  • Challenges: This project was completed shortly after the 2013 Alberta Floods amid a severe shortage of heavy rock riprap. Ironclad had to source over 20,000 tons of riprap from multiple B.C. quarries to meet strict regulatory deadlines. Ironclad also leveraged its network to haul the material during a trucking subcontractor shortage.

Project Timeline

//   May 2023

Drilling & Pressure Grouting

//   May 2024

Sheet Pile Core Wall & Concrete Work

//   July 2024

Embankment Structure

//   September 2024

Spillway and Concrete Work

//   October 2024

Final Dam Commissioning

TESTIMONIAL

Ironclad is a versatile company, and is able to quickly respond to challenging situations with innovative solutions.

Dave Hennigar, Hennigar Consulting | Fort Mcleod Riverbank Stabilization