Ironclad partnered with PCL Construction to deliver Spring Coulee Solar, which is a 42 MW solar project on 204 acres of land outside of Cardston County, Alberta.

KEY DETAILS

Contract Value

$1,859,659

Project Owner

Evolugen by Brookfield Renewable

Completion Date

May 2024

Project Role

Subcontractor

Scope of Work

  • Site grading.
  • Laydown areas.
  • Gravel road construction.
  • Culvert installation.
  • Substation detailed excavation and backfill.
  • Electrical trenching and backfill.
  • ESC measures.
  • Site restoration and seeding.

No items found.

Resources & Challenges

  • Total Crew: 15 Persons
  • Equipment Used:
    3 Excavators, 4 Rock Trucks, 3 Scrapers, 1 Dozer, 1 Grader, 2 Compactors, 
2 Skidsteers.
  • Challenges:
    Ironclad provided multiple crews to overcome significant design changes and volume increase in order to keep the project successfully on schedule.

Project Timeline

//   May 2023

Drilling & Pressure Grouting

//   May 2024

Sheet Pile Core Wall & Concrete Work

//   July 2024

Embankment Structure

//   September 2024

Spillway and Concrete Work

//   October 2024

Final Dam Commissioning

TESTIMONIAL

Ironclad has been highly professional, well-managed, and knowledgeable on all our projects. We look forward to continuing our partnership on future work.

Pat Quinlivan, Construction Manager, PCL Construction | Spring Coulee Solar Project