Demolitions

Stoney 22X Bridge Demolition and Instream Berm Works

Ironclad partnered with PCL Construction for the demolition of a 6-span bridge on Stoney Trail over the Bow River that required a significant instream berm to complete the works.

KEY DETAILS

Contract Value

$2,563,194

Project Owner

Alberta Transportation

Completion Date

July 2024

Project Role

Prime Contractor

Scope of Work

  • Traffic accommodation.
  • Asphalt milling.
  • Bridge demolition.
  • Disposal of contaminated materials.
  • Common excavation.
  • Asphalt paving.
  • Site restoration.

Resources & Challenges

  • Total Crew: 8 Persons
  • Equipment Used:
    2 Excavators, 1 Loader, 1 Skidsteer, 1 Dozer, 1 Compactor, 8 Highway Trucks.
  • Challenges:
    The project was challenged by an aggressive schedule that required the instream berm construction and bride demolition to be completed very quickly. Ironclad responded with two crews that had the required experience to complete both scopes with perfection.

Project Timeline

//   May 2023

Drilling & Pressure Grouting

//   May 2024

Sheet Pile Core Wall & Concrete Work

//   July 2024

Embankment Structure

//   September 2024

Spillway and Concrete Work

//   October 2024

Final Dam Commissioning

TESTIMONIAL