Heavy Civil
Anderson Road SW Widening Initiative
Ironclad partnered with Volker Stevin on a road widening project along Anderson Road SW from Elbow Drive to the transportation utility corridor increasing 4 lanes to 6 lanes. The work comprised significant asphalt roadway removal and detailed earthworks hauling program over the period of three seasons.
KEY DETAILS
■
Contract Value
$1,900,000
■
Project Owner
The City of Calgary
■
Completion Date
September 2019
■
Project Role
Subcontractor
Scope of Work
- Asphalt removal and disposal (including milling).
- Topsoil stripping with offsite removal.
- Roadway common excavation.
- Waste excavation and disposal.
- Detailed earthworks and undercuts.
Resources & Challenges
- Total Crew: 18 Persons
- Equipment Used:
3 Excavators, 3 Dozers, 3 Compactors, 3 Rock Trucks, 2 Scrapers, 20 Highways Trucks.
- Challenges:
Significant roadway removals with off-site disposal and management of sophisticated dirt management program to keep site volumes balanced and paving work progressing.