Commercial Buildings

Banff Homestead Inn Underground Parking Excavation

Ironclad was a subcontractor to CANA Construction for the Banff Homestead Inn project located in Banff, Alberta. The foundation included underground parking that required bulk excavation off-site for this three-story commercial building. 

KEY DETAILS

Contract Value

$1,450,890

Project Owner

Banff Park Lodge

Completion Date

August 2019

Project Role

Subcontractor

Scope of Work

  • Bulk foundation excavation.
  • Detailed excavation and backfill.
  • Secant wall milling.
  • Slab-on-grade preparation.
  • Contaminated material disposal.

No items found.

Resources & Challenges

  • Total Crew: 8 Persons
  • Equipment Used:
    2 Excavators, 1 Loader, 1 Skidsteer, 15 Highway Trucks.
  • Challenges:
    Ironclad overcame the challenge of disposing of bulk excavated material in an out-of-town location. Also, the project specifications had very tight tolerances on the secant pile walls that Ironclad successfully achieved on this project.

Project Timeline

//   May 2023

Drilling & Pressure Grouting

//   May 2024

Sheet Pile Core Wall & Concrete Work

//   July 2024

Embankment Structure

//   September 2024

Spillway and Concrete Work

//   October 2024

Final Dam Commissioning

TESTIMONIAL