Environmental & Remediation
BMO Center Remediation and Expansion
Ironclad partnered with PCL Construction to deliver the BMO Center’s expansion and was responsible for the full excavation of significant contaminated material requiring disposal at a Class II landfill.
KEY DETAILS
■
Contract Value
$1,695,005
■
Project Owner
Calgary Municipal Land Corporation
■
Completion Date
December 2023
■
Project Role
Subcontractor
Scope of Work
- Excavation and disposal of 38,500 tonnes of granular soils impact with Polycyclic Aromatic Hydrocarbons (PAHs)
Resources & Challenges
- Total Crew: 6 Persons
- Equipment Used:
2 Excavators, 1 Loader, 1 Skidsteer, 12 Highway Trucks.
- Challenges:
The impact soil was unforeseen, and Ironclad worked collaboratively with the environmental consultant to manage and export the impacted soils in a timely fashion.