Grading & Earthworks
Shepard Topsoil Bulk Relocation and Hauling
Ironclad acted as Prime Contractor for The City of Calgary and successfully completed a bulk topsoil relocation program that included both hauling on-site and export with disposal.
KEY DETAILS
■
Contract Value
$1,875,400
■
Project Owner
The City of Calgary
■
Completion Date
October 2019
■
Project Role
Prime Contractor
Scope of Work
- Working in sensitive area.
- Topsoil stripping & stockpiling.
- Topsoil export and disposal.
- Final site restoration.
Resources & Challenges
- Total Crew: 7 Persons
- Equipment Used:
2 Excavators, 2 Dozers, 1 Skidsteer, 1 Water Truck, 20 Highway Trucks.
- Challenges:
Topsoil had to be stripped in sensitive area and project required offsite disposal of topsoil in large quantities under short notice.