Grading & Earthworks
Cambridge Park Subdivision Earthworks and Grading
Ironclad acted as prime contractor and successfully completed Cambridge Park Grading, which included bulk earthmoving of over 300,000 m3 on a private subdivision for Amar Developments.
KEY DETAILS
■
Contract Value
$2,741,670
■
Project Owner
AMAR Developments
■
Completion Date
October 2023
■
Project Role
Prime Contractor
Scope of Work
- Stripping to stockpile.
- Mass earthmoving and grading.
- Pond excavation with clay liner.
- Site restoration and seeding
Resources & Challenges
- Total Crew: 10 Persons
- Equipment Used:
4 Scrapers, 2 Dozers, 1 Grader, 2 Compactors, 1 Water Truck, 4 Rock Trucks.
- Challenges:
The client required a very quick turnaround from project award, and Ironclad delivered the project on an aggressive schedule by providing multiple dedicated crews to the project.