Grading & Earthworks

Cambridge Park Subdivision Earthworks and Grading

Ironclad acted as prime contractor and successfully completed Cambridge Park Grading, which included bulk earthmoving of over 300,000 m3 on a private subdivision for Amar Developments.

KEY DETAILS

Contract Value

$2,741,670

Project Owner

AMAR Developments

Completion Date

October 2023

Project Role

Prime Contractor

Scope of Work

  • Stripping to stockpile.
  • Mass earthmoving and grading.
  • Pond excavation with clay liner.
  • Site restoration and seeding
No items found.

Resources & Challenges

  • Total Crew: 10 Persons
  • Equipment Used:
    4 Scrapers, 2 Dozers, 1 Grader, 2 Compactors, 1 Water Truck, 4 Rock Trucks.
  • Challenges:
    The client required a very quick turnaround from project award, and Ironclad delivered the project on an aggressive schedule by providing multiple dedicated crews to the project.

Project Timeline

//   May 2023

Drilling & Pressure Grouting

//   May 2024

Sheet Pile Core Wall & Concrete Work

//   July 2024

Embankment Structure

//   September 2024

Spillway and Concrete Work

//   October 2024

Final Dam Commissioning

TESTIMONIAL

Ironclad's expertise and efficiency ensure project success. Their knowledgeable team delivers exceptional results with professionalism and timeliness—a great partner.

Stacy Oudot, Construction Manager, Standard General | Cambridge Park Project