Heavy Civil
144th Ave Extension Roadway and Bridge Project
Ironclad acted as Subcontractor to Graham Construction to deliver a new infrastructure project that included 1.2 km of new arterial roadway and a new bridge over West Nose Creek. Ironclad successfully completed all earthwork scopes over a two-year period.
KEY DETAILS
■
Contract Value
$12,812,759
■
Project Owner
The City of Calgary
■
Completion Date
August 2023
■
Project Role
Subcontractor
Scope of Work
- Over 100,0000 m3 of bulk earthworks.
- Rock excavation and aggregate material processing.
- Asphalt roadway removal and disposal.
- Supply and installation of 120,000 tonnes of aggregate.
- Roadway grading and subgrade preparation.
- Waste material excavation.
- Structural excavation and backfill.
Resources & Challenges
- Total Crew: 25 Persons
- Equipment Used:
4 Excavators, 8 Rock Trucks, 4 Dozers, 4 Compactors, 1 Grader, 35 x Highway Trucks.
- Challenges:
Management of complex earthworks management plan that underwent significant volume changes on-site requiring Ironclad to act quickly and expedite additional resources to maintain project schedule