Environmental & Remediation

BRCCC Contaminated Material Removal

Ironclad partnered with Clark Builders to deliver the Bridgeland Continuing Care Facility and was responsible for the full excavation of significant contaminated material requiring disposal at a Class II landfill.

KEY DETAILS

Contract Value

$2,700,605

Project Owner

Alberta Infrastructure

Completion Date

September 2024

Project Role

Subcontractor

Scope of Work

  • Excavation and disposal of 20,000 tonnes of granular soils impact with Polycyclic Aromatic Hydrocarbons (PAHs)

No items found.

Resources & Challenges

  • Total Crew: 6 Persons
  • Equipment Used:
    2 Excavators, 1 Loader, 1 Skidsteer, 10 Highway Trucks.
  • Challenges:
    Working collaboratively with an environment consultant, Ironclad managed & exported impacted soils to Class II landfill. Where possible, lesser-impacted soils were repurposed as industrial clean fill at City of Calgary landfills. Additionally, the site had significant buried rubble and debris which required sorting and disposal of both recyclable and waste products.

Project Timeline

//   May 2023

Drilling & Pressure Grouting

//   May 2024

Sheet Pile Core Wall & Concrete Work

//   July 2024

Embankment Structure

//   September 2024

Spillway and Concrete Work

//   October 2024

Final Dam Commissioning